Grangegorman Development Demolition

  • Start Date:
    May 2013
  • Completion Date:
    October 2013
  • Client:
    Grangegorman Development Agency
  • Project Value:

Description of works:

  • Construction of a new haul road to the North Circular Road and associated works on the St Brendan’s campus in Grangegorman, including surfacing, street lighting, installation of services and road markings
  • Condition surveys to neighbouring properties adjoining to the site
  • Carry out asbestos surveys to all buildings
  • Associated works to services including protection and recording of live services to be retained, draining down / disconnections / capping off and the recording of services relating to the structures to be demolished
  • Salvage of materials / treatment, sorting, crushing on site and stockpiling of materials
  • Photography, measurement and assembly of record of selected materials to be salvaged
  • Removal and disposal of materials off site
  • Cataloguing and storing on site of granite elements and stone walls
  • Archaeological works
  • Removal of asbestos containing materials and disposal at off site
  • Demolition of 6 storey former nurses home, brick clad and concrete frame structure
  • Demolition of outlaying hospital structures and sporting facilities
  • Crushing and stockpiling of demolition rubble
  • Erection of Palisade fencing to enclose the site